Fully Encapsulated Scaffold Blasting Project

Commercial

Scaffolded building fully encapsulated in sheeting for dust-controlled blasting in Ireland
During: Scaffolded building fully encapsulated in sheeting for dust-controlled blasting in Ireland
Surface and material
Full building elevation behind scaffold
Existing condition
Elevation requiring blast cleaning in a location where dust and debris had to be fully contained.
The problem
Open blasting was not acceptable on the site, so the works area had to be sealed before any abrasive was used.
Method used
Scaffold fully encapsulated in sheeting, with blasting carried out inside the contained zone.
Work completed
Scaffold sheeted and sealed, blasting completed within the encapsulation, spent abrasive collected inside the containment and removed from site.
Result
Elevation prepared with dust and debris kept entirely within the works area.

Services used on this project